Hulstrom K-8

11551 Wyco Drive, Northglenn, CO, 80233 - 720-972-5400 - Website
Hulstrom building
Project rating - 1 $2.4-$2.9M
Project rating - 1

Construction - Here we go! With the planning and design phase complete, construction is underway at your school to accomplish the individual projects of your school's investment plan.

Latest Updates

A roof restoration and skylight replacement project is scheduled to take place at Hulstrom K-8 in Summer 2021.


Bond improvement took place at Hulstrom K-8 in Summer 2020 and included:

  • Renovations to art and music spaces
  • Extensive crawlspace and plumbing repair work
  • Exterior door/window restoration
  • Sealing work to prevent exterior water intrustion
  • Safety improvements including secured entrance vestibule

Previous bond improvement work took place in Summer 2019 and included:

  • Renovations to the school playground
  • All general education classrooms and the Library Media Center updated with new interactive technology (interactive whiteboard, amplification speaker system, and projectors).

Construction Start Year(s) 

2019: Playground work as listed below in equipment & furnishings- COMPLETED 

2020: All proposed work listed below in building structure [minus roof and skylight replacement], building systems/safety & security, and renovations & remodels - COMPLETED

2021: Roof restoration and skylight replacement as listed below in building structure

Building Structure

  • Repair building structure and systems in the crawlspace - COMPLETED
  • Replace failing skylight systems
  • Roof restoration
  • Seal exterior brick locations to prevent water intrusion - COMPLETED
  • Repair, patch and paint exterior doors and windows to extend service life - COMPLETED

Equipment & Furnishings

  • Replace playground for greater safety and ADA accessibility- COMPLETED 

Building Systems / Safety & Security

  • Replace deteriorating sewer system components - COMPLETED
  • Replace failing water lines - COMPLETED
  • Upgrade school intercom system to meet safety requirements - COMPLETED
  • Install digital security camera system - COMPLETED

Renovations & Remodels

  • Repair or replace arts program items such as easels, pottery wheels, kilns, drafting/drawing stools, airbrush stations, group work stations and A/V systems - COMPLETED
  • Repair or replace music program items such as instrument storage, practice rooms, risers & platforms, acoustic enhancements, auditorium components and A/V systems - COMPLETED

Instructional Upgrades

Each school is provided with funding for instructional upgrades that will be determined through a collaborative process with the school and community. Categories can include furniture, technology, space modifications, safety & security upgrades and specials/electives.